Development of the CSC Docks
The drawings of the docks on this page were based on 1961, 1966,
1982 and 2002 dock plans and other information in the CSC archives.

CSC started in the late 1930s with a single pier and
about 8 slips where the current north gate is now located. The aerial
photo (above) was taken in 1942.

By 1949, there were 12 davits, a pier to the north
with a tool shed and rigging platform at the end, and a pier going
out into the lake.

Davits were added to the north pier and a south pier
was constructed during the 1950s. The configuration above with 51
davits was achieved by 1960.

With two separate piers, the club was turning into
two separate clubs, one to the north and one to the south. A pier
was constructed in 1961 to tie the two clubs together to ensure
that they remained one. 18 additional davits were also added. Willis
McQueen was commodore at the this time

Membership continued to grow as did the demand for
additional davits. In the mid-1960s, 71 additional davits were added.
The south pier was lengthened. Several davits were decked over in
1966 to provide additional common area near the north gate. This
brought the total number of davits to 151 by the end of the 1960s.

There was a flood in 1975 that significantly damaged
the club. The boardboat pads were added as part of the dock repairs.

Davits continued to be high demand. The last davit
expansion program was completed in 1982, when club members built
29 new davits. Ted Perna led members in executing this project who
received one of the new davits for there effort. We have a total
of 178 member owned davits.

The emphasis was then focused on improving the facilities
and the new clubhouse, heads and tackroom, and committee boat davits
were constructed in the late 1980s. The north gazebo, VIP lounge
and junior/SMU lockers were built in the early 1990s. The davits
on the south pier were turned to open to the north to make them
more accessible. In addition, deck, pads and walkway renovations
were started.

New boardboat pads were added north of the Junior/SMU
lockers in 2006. A launch ramp for Optis and board boats was also
added at this time. The old pads were redone in expanded in 2007-08 and a new committee boat daivt structure was completed in 2008.
The aerial photo was taken for the City of Dallas
in 2003.